Maintenance Facility Build Diary |
|
Plans |
|
|
Week 1 |
|
|
|
|
|
Week 2 |
For week 2, Richard has started the scenery process and the building locations have been marked. |
|
|
|
|
Week 3 |
For week 3, Richard installed the track feeds for each of the isolated blocks. |
|
|
|
|
|
|
|
Week 4 |
And here is the progress for week 4. In these pictures, Richard has started adding buildings and ballasting the sidings. |
|
|
|
|
|
|
|
Week 5 |
For week 5, Richard continued working on the ballast and the scenery.
|
In this picture, you can see a close-up of the nearly added undergrowth.
|
In the center of this picture, we have covered the new electrical receptacles to minimize the possible issues with the ballast and scenery materials.
|
In this picture and the next, Richard has been preparing the area (upper right hand corner) for the engine house.
|
|
|
Week 6 |
In this picture, you can see a closeup of the control building foundation with the receptacles covered in blue tap.
|
|
Here is a picture of the roof with the hinges installed.
|
|
Week 7 |
Week 7: Richard has continued working on the building which will contain the control electronics.
|
|
|
|
Week 8 |
Week 8: Here is the progress for week 8. Richard has finished working on the control panel building.
|
|
Week 9 |
Here is the progress for week 9. In these pictures, you can see a closeup of some scenery that Richard is working on.
|
|
|
|
Week 10 |
And here are the photos for week 10. In these pictures, Richard shows some of the repair work on the engine shed.
|
|
In this photo and the next two, you can see the repaired windows.
|
|
|
|
Week 11 |
After some time with the clamps, here is the progress for week 11. In these pictures, Richard shows us the assembled engine shed.
|
|
|
|
Week 12 |
For week 12, Richard worked on the engine shed.
|
|
|
Week 13 |
For week 13, Richard has started installing the buildings on the module.
|
|
|
|
|
Week 14 |
And here is week 14. Richard has finished construction on the maintenance facility module for now.
|
|
|
|
|
|
|
|